Project 7834 — DELPHINUS

  • Home
  • Project 7834 — DELPHINUS
Industrial Engineering Project Portfolio in Chennai with engineering designs
Ballast Water Treatment System Marine Engineering

Project 7834 — DELPHINUS

Client Singapore Based Marine Engineer
Location Singapore
Duration 1 Week
Category BWTS Integration

Scope of Project

Integration of the BWTS Techcross 2600 m³/h system into the DELPHINUS vessel, including equipment location verification, pipeline routing, and clash detection.

BWTS Techcross 2600 m³/h system integration with Delphinus
Equipment location verification based on proposed positions
Mixing line (M) tapping point with 5D distance maintained from Flowmeter per P&ID
Main pipelines and bypass lines routed in compact configuration
Mark-up reference per Slide 3 & 4 for pipeline routing

BWTS Equipment List

The following BWTS equipment locations were verified based on proposed locations as specified:

01 T-Strainer
02 3 × ECU Units
03 Flowmeter
04 Mixing Pump
...

Mixing line tapping point maintained at 5D distance from the Flowmeter as per the project P&ID specification, ensuring compliance with BWTS Techcross installation requirements.

— Project 7834 Technical Specification
Project Summary
  • Project No. 7834
  • Vessel DELPHINUS
  • Client Singapore Marine
  • Category BWTS
  • Location Singapore
  • System Techcross 2600 m³/h
  • Duration 1 Week