Ballast Water Treatment System
Marine Engineering
Project 7834 — DELPHINUS
Client
Singapore Based Marine Engineer
Location
Singapore
Duration
1 Week
Category
BWTS Integration
Scope of Project
Integration of the BWTS Techcross 2600 m³/h system into the DELPHINUS vessel, including equipment location verification, pipeline routing, and clash detection.
•
BWTS Techcross 2600 m³/h system integration with Delphinus
•
Equipment location verification based on proposed positions
•
Mixing line (M) tapping point with 5D distance maintained from Flowmeter per P&ID
•
Main pipelines and bypass lines routed in compact configuration
•
Mark-up reference per Slide 3 & 4 for pipeline routing
BWTS Equipment List
The following BWTS equipment locations were verified based on proposed locations as specified:
01
T-Strainer
02
3 × ECU Units
03
Flowmeter
04
Mixing Pump
![]()
Mixing line tapping point maintained at 5D distance from the Flowmeter as per the project P&ID specification, ensuring compliance with BWTS Techcross installation requirements.
— Project 7834 Technical Specification